Jayaswal Ashoka Infrastructure Private Limited (JAIPL), marked the group's entry into the Infrastructure sector with the undertaking of the BOT Project for design, engineering & construction and the subsequent maintenance and operation of a Bridge near Bhandara city on River Wainganga at a Project Cost of Rs. 422.3 Millions with a concession period of 18 year 9 months which have been further extended by another 6 months. The Project was commissioned for commercial operation in March 2001 and is currently being operated profitably and within projected parameters. The company has securitised its future toll receivables and raised an amount of Rs.430 Mn in April 2006. Having gained invaluable experience in the infrastructure sector, the group is now very enthusiastic and optimistic in commissioning some big prestigious infrastructure projects in the country.
| Important Dates |
| Start Date |
November 1998 |
| Construction Period as per Contract |
30 Months |
| Actual Construction Period |
26 Months |
|
|
|
| Project Details |
| Name of the Project |
Bridge over River Wainganga Km. 491/00 of NAGPUR - RAIPUR ROAD SECTION of N.H. 6 in Bhandara District |
| Funding |
BOT Project for design |
| Client |
MOST and PWD, Government of Maharashtra |
| Concessionaire |
M/s. Jayaswals Ahoka Infrastructure Pvt. Ltd. |
| EPC Contractor |
M/s. BSBK Pvt. Ltd., Bhilai |
| Location |
Bridge near Bhandara city on River Wainganga |
|
|
|